Skip to content
AltUrb
Granted

Rue Général Henry 9

Etterbeek · PU/198947 · Permis d'urbanisme privé

Rue Général Henry 9, Etterbeek: energy works. Case octroyé, lodged on 11 February 2008. The decision was notified on 22 April 2008, 71 days after lodging.

het plaatsen van vier zonnepanelen op het plat dak
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on11 February 2008date the file was received
Decision notified22 April 200871 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
39 mTree fellingabattage d'arbres malades2021
49 mExtension or raisingagrandir, rénover et réaménager une maison unifamiliale ainsi que remplacer les menuiseries extérieures2026
49 mRoofrégulariser la modification des châssis en façade avant et la construction d'une lucarne en façade arrière d'une maison 2025
59 mFaçade and windowsrégulariser les modifications apportées aux façades d'un immeuble d'angle (porte d'entrée, châssis, parement)2023
59 mFaçade and windowsSANS SUITE régulariser et modifier des menuiseries extérieures et éléments de façade en façade à rue2022

Other nearby cases : 05/PU/1955323, 05/PU/1946002, 05/PFD/1928179, 05/PU/1961278, 05/PU/1951701, 05/PU/1800980, 05/PU/1956830, 05/PU/1800750, 05/PU/1948632, 05/AA/1834753, 05/PU/1895714, 05/PU/1927928, 05/PU/1969805, 05/PU/2025615, 05/PU/2003962, 05/PU/1928950, 05/PU/1947191, 05/PU/2027261, 05/PFD/1946827, 05/PU/1915726, 05/PU/2008312, 05/PU/2013020, 05/PU/2036205, 05/PU/1904182, 05/PU/1859780