Granted

Drève des Maricolles 48

Berchem-Sainte-Agathe · PU/203808 · Permis d'urbanisme privé

Drève des Maricolles 48, Berchem-Sainte-Agathe: new construction. Case octroyé, lodged on 4 February 1953. The decision was notified on 7 April 1953, 62 days after lodging.

construction d'un bâtiment
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on4 February 1953date the file was received
Decision notified7 April 195362 days
Floor areasnot reported by the source
Competent authorityBerchem-Sainte-Agathe

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
1 mTree fellingAbattage d'un arbre2021
18 mExtension or raisingExtension et transformation d'une maison unifamiliale2022
46 mDemolition and reconstructiondémolir et reconstruire un volume arrière avec isolation et réaménagement intérieur, dans une maison unifamiliale2026
62 mTree fellingAbattage de 3 arbres2023
72 mRegularisationmise en conformité d'une maison unifamiliale2023

Other nearby cases : 03/PU/2019676, 03/PU/1939481, 03/PU/1865513, 03/PU/1925789, 03/PU/1826918, 03/PU/1826922, 03/PU/1939234, 03/AA/1916226, 03/PU/1820974, 03/PU/2034960, 03/PU/2041422, 03/PU/1959687, 03/PU/1859977, 03/PU/1869072, 03/PU/1870834, 03/PU/1825154, 03/PU/1977419, 03/PU/2019486, 03/PU/1825144, 03/PU/1998710, 03/PU/1989695, 03/PU/1960541, 03/PU/1953944, 03/PU/1983668, 03/PU/1820913

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)