Altaica Urban
Granted

Boulevard Edmond Machtens 55

Molenbeek-Saint-Jean · PU/211602 · Permis d'urbanisme privé

Boulevard Edmond Machtens 55, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 12 August 1959. The decision was notified on 27 November 1959, 107 days after lodging.

la construction d'un immeuble R+5
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on12 August 1959date the file was received
Decision notified27 November 1959107 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
53 mExtension or raisingla surélévation d’un immeuble de rapport avec l’ajout d’un logement au R+3, la régularisation des modifications intérieu2023
66 mExtension or raisingla régularisation des volumes annexes arrières au RDC et R+1 et des modifications de la façade avant, ainsi que l’ajout 2024
68 mOthermodifier la zone de recul2024
68 mOthermodifier la zone de recul2025
68 mOthermodifier la zone de recul2026

Other nearby cases : 12/PU/1942181, 12/PFD/1980898, 12/PU/2019491, 12/SFD/1949590, 12/PU/1935293, 12/PU/1901122, 12/PU/2032857, 12/PFD/2001491, 12/PFD/1948049, 12/PU/1977605, 12/SFD/1857554, 12/PU/1800049, 12/PU/1950339, 12/PU/1826024, 12/PU/1991974, 12/PU/2021689, 12/PU/1897568, 12/PU/1843228, 12/GOU_PU/1859781, 12/PU/2000869, 12/PU/1937191, 12/PFD/1824692, 12/PU/1831396, 12/PFU/1837195, 12/PFU/1971579

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)