Avenue Seghers 1
Molenbeek-Saint-Jean · PU/212393 · Permis d'urbanisme privé
Avenue Seghers 1, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 6 February 1959. The decision was notified on 10 June 1959, 124 days after lodging.
la construction d'un immeuble R+3| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 6 February 1959 | date the file was received |
| Decision notified | 10 June 1959 | 124 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 49 m | Extension or raising | la construction d'un 3ème étage et d'annexes à l'arrière pour la restructuration d'un immeuble de 3 logements | 2022 |
| 49 m | Change of use | la régularisation du changement de destination, aux étages, de 2 logements en équipement (162m2), de la fermeture des te | 2022 |
| 51 m | Façade and windows | isoler les façades par l'extérieur, aux étages et régulariser la modification des châssis | 2025 |
| 51 m | Energy works | Mettre en conformité PEB d’un immeuble à appartements | 2025 |
| 51 m | Regularisation | Mise en conformité de la PEB d'un immeuble à appartement | 2025 |
Other nearby cases : 12/PU/2006192, 12/SFD/2029493, 12/PU/1911109, 11/PU/1906533, 11/PU/2022545, 11/PU/1969254, 11/PU/1895378, 11/PU/1925790, 11/PU/1989876, 11/PU/2034067, 12/PU/1904395, 12/PU/1836204, 12/PU/1859616, 11/PU/1824523, 11/PU/1821088, 11/PU/1897659, 11/PU/1924805, 12/PU/2024152, 11/PU/1847950, 11/GOU_PU/2024501, 11/PFD/2006055, 11/PU/1847728, 12/PU/2025200, 11/PU/2016501, 11/PFD/1867151
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)