Granted
Boulevard Edmond Machtens 149–159
Molenbeek-Saint-Jean · PU/215028 · Permis d'urbanisme privé
Boulevard Edmond Machtens 149–159, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 3 April 1973. The decision was notified on 13 July 1973, 101 days after lodging.
la construction d'un iimmeuble R+22| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 April 1973 | date the file was received |
| Decision notified | 13 July 1973 | 101 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 45 m | Tree felling | Abattre 3 peupliers occasionnant des infiltrations au niveau des parking sous-terrain de l'immeuble arc en ciel. | 2024 |
| 45 m | Tree felling | Abattre un gros saule sur le site dit "Arc-En-Ciel". Le pied présentait d'importante pourritures, le risque de chute éta | 2025 |
| 47 m | Tree felling | Abattre un érable causant des infiltrations dans le parking sous-terrain de l'immeuble Arc en ciel. | 2024 |
| 82 m | Tree felling | l'abattage d'un arbre sur le domaine public, inscrit à l'inventaire du patrimoine naturel, suite au permis PU-37.957 dél | 2021 |
| 97 m | Public space | Fermer la berme centrale sur le bd. Louis Mettewie à hauteur du carrefour formé par le bd. et les avenues du Condor et M | 2024 |
Other nearby cases : 12/PU/1986908, 12/PU/1907894, 12/PU/1895932, 12/PU/2033523, 12/PU/1854867, 12/PU/1987827, 12/PU/1946218, 12/PU/2039456, 12/SFD/1960515, 12/PU/2007575, 12/PU/1929436, 12/PFD/1857138
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)