Altaica Urban
Refused

Rue de la Belle au Bois Dormant 25

Molenbeek-Saint-Jean · PU/215422 · Permis d'urbanisme privé

Rue de la Belle au Bois Dormant 25, Molenbeek-Saint-Jean: new construction. Case refusé, lodged on 10 March 1992. The decision was notified on 7 August 1992, 150 days after lodging.

la construction d'un immeuble R+3+ET
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusRefusé
Lodged on10 March 1992date the file was received
Decision notified7 August 1992150 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Refused

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)