Granted

Boulevard Louis Mettewie 74–76

Molenbeek-Saint-Jean · PU/215771 · Permis d'urbanisme privé

Boulevard Louis Mettewie 74–76, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 5 July 1979. The decision was notified on 21 March 1980, 260 days after lodging.

la construction d'un immeuble bureaux R+6
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on5 July 1979date the file was received
Decision notified21 March 1980260 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
1 mEnergy worksla mise en place et le raccordement d'une cabine haute tension de 800Kva2023
1 mSigns and advertisingplacement de 2 enseignes"Partenamut" en façade et en toiture, ainsi que le remplacement d’un totem, d’un l’immeuble en R2023
1 mOtherla mise en place et le raccordement d'une cabine haute tension de 800Kva2022
1 mExtension or raisingConstruire un monte-charge extérieur, un auvent semi-fermé, une dalle technique et un espace fumeurs pour un bâtiments d2025
1 mExtension or raisingla construction d’un monte-charge extérieur, d’un auvent semi-fermé, d’une dalle technique et d’un espace fumeurs, pour 2025

Other nearby cases : 12/PU/2028081, 12/PFD/1915227, 12/PU/1868943, 12/SFD/1947332, 12/PU/1930623, 12/PFD/1937723, 12/PU/1861711, 12/PU/1837271, 12/PU/2007575, 12/PU/1845223, 12/PU/1811556