Rue de la Fraîcheur 17

Molenbeek-Saint-Jean · PU/216106 · Permis d'urbanisme privé

Rue de la Fraîcheur 17, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 19 May 1982. The decision was notified on 18 June 1982, 30 days after lodging.

immeuble R+3
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on19 May 1982date the file was received
Decision notified18 June 198230 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
10 mMerger of dwellingsla régularisation, suite au non-respect du permis PU-31.048, de la réunification de deux appartements au 4ème étage (imm2021
69 mTree fellingl’abattage d'un arbre à haute tige (cyprès)2023
73 mRoofla régularisation de l'aménagement des combles en duplex avec le 2ème étage d'un immeuble de rapport et de la modificati2022
78 mChange of usele changement d’utilisation des combles non habitables en logement et la régularisation du changement d’utilisation d’un2024
78 mExtension or raisingla rehausse d'un étage d’un immeuble de rapport en R+2+T pour la création d’un logement 2 chambres2025

Other nearby cases : 12/GOU_PU/1945101, 12/PU/1914994, 12/PU/1820386, 12/LPFD/1838931, 12/PFD/2001491, 12/PU/1901122, 12/PU/1800653, 12/PU/1843228, 12/GOU_PU/1859781, 12/SFD/1949590, 12/PU/1935293, 12/PU/2021689, 12/SFD/2021901, 12/PU/1987184, 12/PU/2019491, 12/PFD/1999535, 12/PFD/2035546, 12/PU/1958357, 12/PFD/1925384, 12/PU/1908683, 12/PU/1958706, 12/GOU_PU/2016931, 12/PU/1958358, 12/GOU_PU/2000206, 12/PU/1977605

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)