Skip to content
Altaica Urban
Refused

Chaussée de Ninove 183

Molenbeek-Saint-Jean · PU/216515 · Permis d'urbanisme privé

Chaussée de Ninove 183, Molenbeek-Saint-Jean: new construction. Case refusé, lodged on 27 August 1987. The decision was notified on 17 June 1988, 295 days after lodging.

complexe commercial avec station-service
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusRefusé
Lodged on27 August 1987date the file was received
Decision notified17 June 1988295 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Refused

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.