Avenue du Château 1, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 8 February 1990. The decision was notified on 2 August 1991, 540 days after lodging.

bâtiment R+1 (cafétaria, vestiaires) + couvr. 3 terr. tenn.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on8 February 1990date the file was received
Decision notified2 August 1991540 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.