Granted

Rue des Hippocampes 18

Molenbeek-Saint-Jean · PU/216881 · Permis d'urbanisme privé

Rue des Hippocampes 18, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 19 February 1990. The decision was notified on 6 April 1990, 46 days after lodging.

maison R+2
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on19 February 1990date the file was received
Decision notified6 April 199046 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
80 mNew constructionla construction d'un immeuble de rapport mitoyen (R+4) comprenant 9 logements et 8 emplacements parking en sous-sol PM: 2023
80 mNew constructionla construction d'un immeuble de rapport mitoyen (R+4) comprenant 9 logements et 8 emplacements parking en sous-sol PM: 2024
89 mNew constructionconstruire un immeuble comprenant 41 logements d'une surface totale de 4 614,7m², 240,3m² de surface commercial, 349,4m2024
91 mTree fellingAbattre cinq arbres à haute tige dans l' arrière jardin privé2022
112 mFaçade and windowsla rénovation des terrasses et le remplacement des garde-corps en façade avant d’un immeuble en R+3+ET2025

Other nearby cases : 12/PU/1819984, 12/PU/1906371, 12/PU/1939148, 12/SFD/2015184, 12/PU/1930623, 12/PU/1916249, 12/PU/1966309, 12/PU/1871760, 12/GOU_PU/1996073, 12/PU/2043131, 12/PU/1811556, 12/PU/1949670, 12/PU/1957594, 12/PU/1799784, 12/PU/1914080, 12/PFD/2014049, 12/PU/2028081, 12/SFD/1925015, 12/PU/2016749, 12/PU/1854748, 12/PFD/1999535, 12/PFD/2035546, 12/PFD/1915227, 12/PFD/1925384, 12/SFD/1944657

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)