Granted
Avenue des Amandiers 19
Molenbeek-Saint-Jean · PU/217106 · Permis d'urbanisme privé
Avenue des Amandiers 19, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 15 March 1991. The decision was notified on 19 April 1991, 35 days after lodging.
unifamiliale R+2| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 March 1991 | date the file was received |
| Decision notified | 19 April 1991 | 35 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 27 m | Extension or raising | la régularisation de la modification de la façade, de la construction d'une cave supplémentaire, de l'agrandissement de | 2023 |
| 39 m | New construction | la construction d'un immeuble R+3+étage en recul de 13 logements et d'un parking sous terrain de 8 emplacements de parki | 2026 |
| 80 m | Public space | Aménager une plaine de jeux et d'un street workout dans le Parc Hauwaert | 2022 |
| 80 m | Tree felling | Abattre 9 arbres dépérissants et présentant un danger pour les usager.e.s du bois Hauwaert | 2026 |
| 120 m | Split into dwellings | diviser une maison unifamiliale en 3 logements par l'extension des 3 niveaux et la création d'une terrasse au 1er étage, | 2024 |
Other nearby cases : 12/PU/1941839, 12/PU/1843027, 12/PU/1844200, 12/PU/1845223, 12/PU/1970037, 12/PU/1996597, 12/PFD/1984694, 12/PU/1946218, 12/PU/2039456, 12/SFD/1960515
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)