Skip to content
AltUrb
Granted

Rue des Hippocampes 4

Molenbeek-Saint-Jean · PU/217155 · Permis d'urbanisme privé

Rue des Hippocampes 4, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 8 August 1991. The decision was notified on 18 October 1991, 71 days after lodging.

la construction d'une immeuble R+3
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on8 August 1991date the file was received
Decision notified18 October 199171 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
51 mFaçade and windowsla rénovation des terrasses et le remplacement des garde-corps en façade avant d’un immeuble en R+3+ET2025
105 mNew constructionla construction d'un immeuble de rapport mitoyen (R+4) comprenant 9 logements et 8 emplacements parking en sous-sol PM: 2024
105 mNew constructionla construction d'un immeuble de rapport mitoyen (R+4) comprenant 9 logements et 8 emplacements parking en sous-sol PM: 2023
136 mTree fellingAbattre cinq arbres à haute tige dans l' arrière jardin privé2022
146 mOtherl'ajout d'un escalier d’accès au jardin arrière d'une maison unifamiliale en R+12023

Other nearby cases : 12/PFD/1937723, 12/PU/2043131, 12/PU/1957594, 12/PFD/2035546, 12/PU/1949670, 12/PFD/1999535, 12/PFD/1925384, 12/PU/1819984, 12/PU/1916249, 12/PU/1943162, 12/PU/1958706, 12/PU/1939148, 12/SFD/2015184, 12/PU/1914994, 12/GOU_PU/1945101, 12/PU/1966309, 12/GOU_PU/1996073, 12/PU/1871760, 12/PU/1930623, 12/PU/1820386, 12/PU/1833070, 12/PU/2016749, 12/PU/2028081, 12/SFD/1925015, 12/PU/1914080

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)