Quai des Charbonnages 62, Molenbeek-Saint-Jean: office conversion. Case octroyé, lodged on 24 November 2006. The decision was notified on 7 November 2007, 348 days after lodging.
changement d'affectation d'un immeuble de bureaux en 8 logements comportant 5 parkings au sous-sol, 13 parkings et un commerce (200m²) au rez-de-chaussée et construction d'un 6éme étage| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 November 2006 | date the file was received |
| Consultation committee | 29 May 2007 | |
| Decision notified | 7 November 2007 | 348 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.