Avenue du Sippelberg 6–8
Molenbeek-Saint-Jean · PU/219195 · Permis d'urbanisme privé
Avenue du Sippelberg 6–8, Molenbeek-Saint-Jean: demolition and reconstruction. Case octroyé, lodged on 5 February 2007. The decision was notified on 27 September 2007, 234 days after lodging. It comprises 84 dwellings.
la démolition d'un bâtiment et la reconstruction de 2 immeubles de 84 logements comportant un parking en sous-sol pour 84 véhicules (rez-de-chaussée et 3-4 étages)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 5 February 2007 | date the file was received |
| Consultation committee | 26 June 2007 | |
| Decision notified | 27 September 2007 | 234 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 95 m | Energy works | l'implantation de panneaux solaires sur structure portantes (724m2) | 2023 |
| 113 m | — | 12/PFU/2044705 | 2026 |
| 140 m | New construction | La régularisation d'une construction d'un préau de 150 m² | 2021 |
| 140 m | New construction | Construire un préau de 150m² sur la cour de l'école de l'Athénée Royale du Sippelberg. | 2021 |
| 140 m | New construction | La régularisation d'une construction d'un préau de 150 m² | 2021 |
Other nearby cases : 12/PU/1911645, 12/PU/1914501, 12/PU/1853644, 12/PU/1836204, 12/PU/2038577, 12/PU/1904395, 12/PU/2033654, 12/PU/2005484, 12/PU/2012397, 12/PU/1822966, 12/PU/1961643, 12/PU/2025200, 12/PU/1911109, 12/PU/1909296, 12/SFD/1933350, 12/PU/1855587, 12/PU/1856305, 12/PU/1995351, 12/PU/1866822, 12/PFD/1854074, 12/PU/1853201, 12/PU/2006192, 12/SFD/2029493, 12/PFD/2005985, 12/PU/2043686
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)