Granted
Rue Jean Verbiest 32
Molenbeek-Saint-Jean · PU/219316 · Permis d'urbanisme privé
Rue Jean Verbiest 32, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 30 July 2007. The decision was notified on 16 April 2008, 261 days after lodging. It comprises 3 dwellings.
construction d'un immeuble comprenant 3 logements3
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 July 2007 | date the file was received |
| Consultation committee | 23 October 2007 | |
| Decision notified | 16 April 2008 | 261 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)