Granted
Rue de la Houlette 40–42
Watermael-Boitsfort · PU/222189 · Permis d'urbanisme privé
Rue de la Houlette 40–42, Watermael-Boitsfort: new construction. Case octroyé, lodged on 4 November 2003. The decision was notified on 20 July 2004, 259 days after lodging. It comprises 27 dwellings.
construire un ensemble de 27 appartements et partiellement régulariser des travaux en exécution sur base du permis d'urba délivré le 06/02/2001 par le collège des Bourgmestre et Echevins de Watermael-Boitsfort à Monsieur Thierry de PRÊT ROOSE de CALESBERG27
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 November 2003 | date the file was received |
| Public inquiry | 2 February 2004 – 17 February 2004 | |
| Consultation committee | 30 March 2004 | |
| Decision notified | 20 July 2004 | 259 days |
| Floor areas | — | not reported by the source |
| Competent authority | Watermael-Boitsfort |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)