Granted

Rue de la Houlette 40–42

Watermael-Boitsfort · PU/222189 · Permis d'urbanisme privé

Rue de la Houlette 40–42, Watermael-Boitsfort: new construction. Case octroyé, lodged on 4 November 2003. The decision was notified on 20 July 2004, 259 days after lodging. It comprises 27 dwellings.

construire un ensemble de 27 appartements et partiellement régulariser des travaux en exécution sur base du permis d'urba délivré le 06/02/2001 par le collège des Bourgmestre et Echevins de Watermael-Boitsfort à Monsieur Thierry de PRÊT ROOSE de CALESBERG
The application's own description, in its source language (FR). Source: Nova.
27
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on4 November 2003date the file was received
Public inquiry2 February 2004 – 17 February 2004
Consultation committee30 March 2004
Decision notified20 July 2004259 days
Floor areasnot reported by the source
Competent authorityWatermael-Boitsfort

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)