Skip to content
Altaica Urban
Granted

Rue Jean-Baptiste Meunier 3

Ixelles · PU/230265 · Permis d'urbanisme privé

Rue Jean-Baptiste Meunier 3, Ixelles: new construction. Case octroyé, lodged on 28 October 1998. The decision was notified on 20 September 1999, 327 days after lodging.

réalisation d'une cours parking et bureaux
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on28 October 1998date the file was received
Decision notified20 September 1999327 days
Floor areasnot reported by the source
Competent authorityIxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)