Granted
Chaussée d'Ixelles
Ixelles · PU/231803 · Permis d'urbanisme privé
Chaussée d'Ixelles, Ixelles: public space. Case octroyé, lodged on 15 July 2003. The decision was notified on 7 May 2004, 297 days after lodging.
MM installation d'un ascenseur d'accessibilité au P.M.R. (station de métro Porte de Namur)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 July 2003 | date the file was received |
| Public inquiry | 25 August 2003 – 9 September 2003 | |
| Consultation committee | 17 September 2003 | |
| Decision notified | 7 May 2004 | 297 days |
| Floor areas | — | not reported by the source |
| Competent authority | Ixelles |
Timeline
- Declared complete
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)