Avenue Adolphe Buyl 2, Ixelles: heavy renovation. Case octroyé, lodged on 3 August 2007. The decision was notified on 26 May 2008, 297 days after lodging.
réaménagement et raffaichissement des 4 appartements au niveau des 1er et 2ème étages, mise en confromité des 2 appartements, au niveau du grenier, et des annexes construites à l'arrière au niveau du 2ème étage et entre-sol, couverture de la cour existant| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 August 2007 | date the file was received |
| Public inquiry | 12 November 2007 – 27 November 2007 | |
| Consultation committee | 12 December 2007 | |
| Decision notified | 26 May 2008 | 297 days |
| Floor areas | — | not reported by the source |
| Competent authority | Ixelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.