Rue de la Grosse Tour 26, Ixelles: new construction. Case octroyé, lodged on 14 August 2009. The decision was notified on 12 March 2010, 210 days after lodging.

mettre en conformité la construction d'un boxe de garage
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on14 August 2009date the file was received
Consultation committee21 October 2009
Decision notified12 March 2010210 days
Floor areasnot reported by the source
Competent authorityIxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)