Granted

Rue du Moulin à Vent 29

Evere · PU/238380 · Permis d'urbanisme privé

Rue du Moulin à Vent 29, Evere: new construction. Case octroyé, lodged on 26 October 1948. The decision was notified on 26 October 1948, 0 days after lodging.

construire une maison unifamiliale
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on26 October 1948date the file was received
Decision notified26 October 19480 days
Floor areasnot reported by the source
Competent authorityEvere

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
23 mExtension or raisingreconstruire l'extension d'une maison unifamiliale2025
31 mHeavy renovationmettre en conformité les transformations apportées à l'appartement du rez-de-chaussée droit2022
31 mFaçade and windowsmettre en conformité le remplacement de la porte d'entrée.2023
34 mExtension or raisingmettre en conformité les travaux réalisés à l'appartement du rez-de-chaussée (fermeture de la cour et de la terrasse, mo2023
42 mRegularisationMettre en conformité des modifications de l'immeuble2024

Other nearby cases : 06/PFU/1831200, 06/PFU/1896040, 06/PU/1991913, 06/PU/1935310, 06/PU/1840660, 06/PU/2042875, 06/PU/1921662, 06/PU/2019936, 06/PU/1972549, 06/PU/1858578, 06/PU/2032618, 06/PU/1905497, 06/PU/2030088, 06/PU/1971698, 06/PU/1938549, 06/PU/1905927, 06/PU/1896501, 06/SFD/1827176, 06/PU/1823633, 06/PU/2040719, 06/PU/2022372, 06/PFD/1869445, 06/PU/1837821, 06/PU/2010376, 06/PU/1860910