Granted
Rue Colonel Bourg 156A
Evere · PU/244135 · Permis d'urbanisme privé
Rue Colonel Bourg 156A, Evere: new construction. Case octroyé, lodged on 29 May 2007. The decision was notified on 22 April 2008, 329 days after lodging.
Construction d'une maison de répit| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 29 May 2007 | date the file was received |
| Public inquiry | 21 December 2007 – 12 January 2008 | |
| Consultation committee | 17 January 2008 | |
| Decision notified | 22 April 2008 | 329 days |
| Floor areas | — | not reported by the source |
| Competent authority | Evere |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.