Skip to content
Altaica Urban
Granted

Chaussée de Bruxelles 60

Forest · PU/245788 · Permis d'urbanisme privé

Chaussée de Bruxelles 60, Forest: new construction. Case octroyé, lodged on 23 June 1879. The decision was notified on 23 June 1879, 0 days after lodging.

Construction d'une maison (Elévation+coupe+plan)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on23 June 1879date the file was received
Decision notified23 June 18790 days
Floor areasnot reported by the source
Competent authorityForest

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
39 mTree fellingAbattage de 4 arbres à l'intérieur d'ilot. 2021
41 mTree fellingabattre 2 arbres à haute tige2024
50 mChange of usemodifier le nombre de logements de 2 à 4 par la construction de 2 nouveaux étages avec aménagement de balcons arrières, 2026
50 mExtension or raisingmodifier le nombre de logements de 2 à 3 (dont 1 duplex) par la construction de 2 nouveaux étages avec aménagement d'une2026
50 mChange of usemodifier le nombre de logements de 2 à 4 par la construction de 2 nouveaux étages avec aménagement de balcons arrières, 2025

Other nearby cases : 07/PU/1938463, 07/PU/1835220, 07/PU/1913530, 07/PU/2036349, 07/PU/1951718, 07/PFD/1892187, 07/PFD/2039228, 07/GOU_PU/1859803, 07/PFD/1822129, 07/PU/2027576, 07/PFD/1944970, 07/PU/1959228, 07/PU/1871316, 07/PU/1903024, 07/PU/2039008, 07/PU/1960616, 07/PU/1935760, 07/PU/1963915, 07/PFU/1960607, 07/PU/1897428, 07/PU/1961718, 07/PU/1943929, 07/PU/1911745, 07/PU/1828466, 07/PFD/1924409

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)