Chaussée de Ruisbroek 115, Forest: new construction. Case octroyé, lodged on 3 June 1921. The decision was notified on 3 June 1921, 0 days after lodging.
bâtiments industrielsn¿115/115A/117| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 June 1921 | date the file was received |
| Decision notified | 3 June 1921 | 0 days |
| Floor areas | — | not reported by the source |
| Competent authority | Forest |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 89 m | Change of use | implanter une activité récréative dans un hall industriel existant; régulariser le Hall contigu; modifier la disposition | 2022 |
| 89 m | Change of use | Régularisation les modifications de la salle 1 suite au permis 07/PFD/619741 (d.d. 31/07/2017) Changer l'affectation de | 2023 |
| 120 m | Retail or horeca fit-out | aménager un show-room au niveau du parking | 2022 |
| 138 m | Public space | Aménager la Promenade Verte régionale le long de la rue des Lutins à Forest. | 2022 |
| 159 m | Other | Renforcer son réseau de communications entre ses véhicules (Bus, Trams) et ses centres de contrôle, la STIB souhaite imp | 2026 |
Other nearby cases : 07/PU/2009562, 07/PU/2024902, 07/PFD/2026786, 07/PU/1800505, 07/PU/1835233, 16/PU/2025095, 07/PU/1990263, 07/SFD/1799672, 07/PU/1961533, 07/PFD/1943218, 07/PU/1944441, 07/PU/1991417, 07/PU/2010509