Skip to content
Altaica Urban
Granted

Avenue Oscar Van Goidtsnoven 45

Forest · PU/253413 · Permis d'urbanisme privé

Avenue Oscar Van Goidtsnoven 45, Forest: new construction. Case octroyé, lodged on 14 December 1923. The decision was notified on 14 December 1923, 0 days after lodging.

atelier carrosserie (fond)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on14 December 1923date the file was received
Decision notified14 December 19230 days
Floor areasnot reported by the source
Competent authorityForest

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
9 mFaçade and windowsCADUQUE - forer la façade avant afin d'installer un ventilation2024
13 mSplit into dwellingsaménager les combles pour un logement supplémentaire via la construction d'une lucarne sur le pan arrière de la toiture 2023
22 mExtension or raisingmettre en conformité la fermeture partielle du balcon en façade arrière au 2ième étage2026
22 mExtension or raisingMISE SANS SUITE - mettre en conformité la fermeture partielle du balcon en façade arrière au 2ième étage de l'immeuble2026
22 mExtension or raisingmettre en conformité la fermeture du balcon en façade arrière et transformer l'intérieur d'un appartement 1 chambre au 32025

Other nearby cases : 07/PU/1868926, 07/PU/1956282, 16/PFD/2011453, 16/PU/1993335, 07/PU/1810806, 07/SFD/1832170, 16/PU/1958655, 16/PU/1839741, 07/PU/1991206, 07/PU/2023607, 07/PU/1837627, 07/PU/1995421, 16/PU/1930920, 16/PU/1849797, 07/PFU/2022451, 07/PU/1960091, 07/PU/2022716, 16/PU/1800015, 07/PU/1826205, 16/PU/1951284, 16/PU/1949681, 16/PU/2017566, 07/PU/1978391, 07/PU/1846884, 07/PU/1822589

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)