Avenue Molière 101, Forest: —. Case octroyé, lodged on 22 April 1927. The decision was notified on 22 April 1927, 0 days after lodging.

maison
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on22 April 1927date the file was received
Decision notified22 April 19270 days
Floor areasnot reported by the source
Competent authorityForest

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
19 mRoofAménager une terrasse sur le toit d'un immeuble2022
53 mHeavy renovationmodifier la structure intérieure du logement situé au 5ème étage côté gauche2026
53 mMerger of dwellingsModifier la répartition et le nombre de logements (de 13 à 12) par la création d'un duplex rez-de-chaussée/1er étage dro2022
53 mSplit into dwellingsModifier la répartition et le nombre de logements (de 13 à 12) par la création d'un duplex rez-de-chaussée/1er étage dro2021
53 mExtension or raisingmettre en conformité la fermeture de la terrasse située au côté gauche du 5ème étage2025

Other nearby cases : 07/PU/1925485, 07/PU/2044129, 07/PU/1903116, 07/PU/2037095, 07/PU/2036675, 07/PU/2036047, 07/PU/2016133, 07/PU/1828741, 07/PU/1852632, 07/PU/1823391, 16/PU/1990260, 07/PU/1830553, 16/PU/1980627, 07/PU/1829101, 07/PFU/1858278, 07/PFU/1902643, 07/PFU/1830046, 07/PU/2019007, 07/PU/1828457, 07/SFD/1843838, 07/SFD/1837291, 07/PU/1821717, 07/PU/1830441, 07/PU/2000795, 07/PU/2018589