Skip to content
AltUrb
Granted

Avenue Maréchal Joffre 124

Forest · PU/260428 · Permis d'urbanisme privé

Avenue Maréchal Joffre 124, Forest: extension or raising. Case octroyé, lodged on 3 February 1948. The decision was notified on 3 February 1948, 0 days after lodging.

maison+surél.le 11/05/1948
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on3 February 1948date the file was received
Decision notified3 February 19480 days
Floor areasnot reported by the source
Competent authorityForest

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingTransformation et extension d'une maison unifamiliale.2022
0 mExtension or raisingTransformation et extension d'une maison unifamiliale.2021
39 mOtherInstaller de nouveaux équipements de télécommunication mobile pour TELENET sur la toiture d'un bâtiment existant à Uccl2025
65 mSplit into dwellingsDemande pour réduire le nombre des logements de 3 à 4 plus régularisation feronnerie retirée et châssis en façade avant 2026
65 mSplit into dwellingsaménager les combles pour un logement supplémentaire via la construction d'une lucarne sur le pan arrière de la toiture 2023

Other nearby cases : 07/PU/2022716, 07/PU/1960091, 16/PU/1948379, 07/PU/1901046, 07/PU/1860180, 07/PU/1810819, 07/PU/2018461, 07/PU/1868926, 07/PU/1956282, 16/PU/1997053, 16/PU/2041952, 16/PU/2032658, 07/PU/1856730, 07/PU/1940289, 16/PU/1993335, 16/PU/1839741, 07/PU/1846373, 07/SFD/1811412, 07/PU/1831753, 07/GOU_PU/1902368, 07/PU/1996550, 16/PU/2014994, 16/PU/1849797, 16/PU/1930920, 07/PU/1862959

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)