Granted
Boulevard de l'Humanité 292
Forest · PU/267414 · Permis d'urbanisme privé
Boulevard de l'Humanité 292, Forest: heavy renovation. Case octroyé, lodged on 18 January 1996. The decision was notified on 18 September 1996, 244 days after lodging.
rénovation immeuble et façade à rue| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 January 1996 | date the file was received |
| Decision notified | 18 September 1996 | 244 days |
| Floor areas | — | not reported by the source |
| Competent authority | Forest |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 1 m | Other | Réaménager des emplacements de parking extérieur | 2022 |
| 150 m | Demolition and reconstruction | Démolir et reconstruire des bâtiments d'entrepôts logistiques, modifications des circulations, avec un parking couvert | 2022 |
| 180 m | Façade and windows | mettre en conformité les modifications de baies, de circulation extérieure, la modification du parking couvert passant d | 2024 |
| 192 m | New construction | Construire et exploiter une grande éolienne et ses accessoires dans le cadre de la production d'énergie verte, installer | 2024 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)