Granted
Rue du Charroi 0
Forest · PU/267758 · Permis d'urbanisme privé
Rue du Charroi 0, Forest: public space. Case octroyé, lodged on 19 May 1998. The decision was notified on 20 October 1998, 154 days after lodging.
construction d'un collecteur d'eaux usées (phase 2)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 May 1998 | date the file was received |
| Decision notified | 20 October 1998 | 154 days |
| Floor areas | — | not reported by the source |
| Competent authority | Forest |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)