Granted

Boulevard de l'Humanité 124

Forest · PU/268464 · Permis d'urbanisme privé

Boulevard de l'Humanité 124, Forest: new construction. Case octroyé, lodged on 29 August 2002. The decision was notified on 19 December 2002, 112 days after lodging.

construction d'un abri pour matériel technique
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on29 August 2002date the file was received
Decision notified19 December 2002112 days
Floor areasnot reported by the source
Competent authorityForest

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
83 mSigns and advertisingInstaller un dispositif publicitaire digital de 2 m² (MU783) à hauteur du n°122 boulevard Industriel 2023
88 mSigns and advertisingMaintenir un panneau publicitaire non éclairé de 20 m², situé sur un talus à proximité du boulevard Industriel 116.2024
186 mSigns and advertisingmaintenir un dispositif publicitaire de 15m²2025
192 mChange of usechanger l'affectation d'un centre de véhicules d'occasion en entrepôt avec show-room2023
211 mSigns and advertisingmaintenir un dispoisitif publicitaire de 36 m²2025

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)