Skip to content
AltUrb
Granted

Boulevard du Souverain 147a

Auderghem · PU/279238 · Permis d'urbanisme privé

Boulevard du Souverain 147a, Auderghem: façade and windows. Case octroyé, lodged on 5 February 2010. The decision was notified on 26 August 2010, 202 days after lodging.

modifier, en cours de chantier, le permis d'urbanisme n° 13820 (division de châssis et abords)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on5 February 2010date the file was received
Consultation committee19 May 2010
Decision notified26 August 2010202 days
Floor areasnot reported by the source
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Consultation committee
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
14 mChange of usemettre en conformité le changement d'affectation d'une partie du rez-de-chaussée, isoler la façade arrière, les murs mit2024
23 mHeavy renovationtransformer deux immeubles2026
26 mChange of usechanger la destination du commerce2026
51 mChange of usechanger la destination d'une boucherie en restaurant ainsi que créer deux ouvertures et installer la climatisation sur l2026
59 mSigns and advertisingplacer 2 enseignes2022

Other nearby cases : 02/PU/1841230, 02/GOU_PU/1870552, 02/PP/1906459, 02/PU/1828260, 02/PU/1922659, 02/ENS/1966796, 02/PU/1955524, 02/PU/1966811, 02/PU/2026770, 02/PU/1988663, 02/PU/1858471, 02/PU/1801301, 02/PU/1907206, 02/PU/1925153, 02/PU/1949551, 02/PU/2011985, 02/PU/2019426, 02/PU/1973241, 02/PU/1924580, 02/PU/1864369, 02/PU/1833449, 02/AA/1922273, 02/ENS/2005958, 02/PP/1839526, 02/PU/1953202