Skip to content
Altaica Urban
Granted

Rue Adolphe De Brandt 40

Evere · PU/285736 · Permis d'urbanisme privé

Rue Adolphe De Brandt 40, Evere: heavy renovation. Case octroyé, lodged on 9 September 2010. The decision was notified on 14 December 2010, 96 days after lodging. The project creates 9 m² of housing.

wijzigen van de stedenbouwkundigevergunning nr 2005-154 : verbouwing van de 4de verdieping.
The application's own description, in its source language (NL). Source: Nova.
9
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on9 September 2010date the file was received
Decision notified14 December 201096 days
Competent authorityEvere

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)