Granted

Rue de la Procession 26

Anderlecht · PU/290522 · Permis d'urbanisme privé

Rue de la Procession 26, Anderlecht: new construction. Case octroyé, lodged on 18 April 1884. The decision was notified on 18 April 1884, 0 days after lodging.

construire un four avec fournil
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on18 April 1884date the file was received
Decision notified18 April 18840 days
Floor areasnot reported by the source
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
47 mExtension or raisingtransformer une habitation unifamiliale avec changement de volume2022
50 mSigns and advertisingdemande de renouvellement de 4 bornes publicitaires ayant déjà fait objet d'un précédent PU avec la ref 01/PFD/1719762 d2026
51 mMerger of dwellingsmettre en conformité un immeuble de rapport en maison unifamiliale comme le prescrit la situation de droit2022
72 mFaçade and windowschanger les châssis pour l'ensemble du bâtiment2023
84 mExtension or raisingétendre l’appartement et transformer l'espace jardin au rez-de-chaussée d’un immeuble de logements2024

Other nearby cases : 01/PU/1901768, 01/PU/1911481, 01/PU/1925611, 01/PU/2035500, 01/SFD/1996189, 01/PU/1827856, 01/PU/1927735, 01/PU/1968207, 01/PU/1978844, 01/PU/1852499, 01/PU/1918999, 01/PU/1901588, 01/PU/1994033, 01/PU/2014068, 01/PU/1896429, 01/PU/2028897, 01/SFD/2005161, 01/PU/1975567, 01/AA/1912452, 01/SFD/1991959, 01/PU/2036192, 01/PU/1965369, 01/PU/1847017, 01/SFD/1923910, 01/PU/1911510