Rue Bara 3
Anderlecht · PU/291344 · Permis d'urbanisme privé
Rue Bara 3, Anderlecht: new construction. Case octroyé, lodged on 29 July 1887. The decision was notified on 29 July 1887, 0 days after lodging.
construire une maison (6,60m)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 29 July 1887 | date the file was received |
| Decision notified | 29 July 1887 | 0 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 6 m | Split into dwellings | régulariser le bâtiment, modifier le nombre de logements et transformer la façade à rue (PV 2021/3918) | 2023 |
| 6 m | Change of use | diviser une maison unifamiliale en 2 unités d'habitation, changer l'affectation de l'Horeca en commerce + mettre en conf | 2025 |
| 11 m | Split into dwellings | mettre en conformité l’augmentation du nombre de logements (de 1 à 3), réaménager les logements et modifier la façade av | 2026 |
| 33 m | Public space | Demande de Permis d'Urbanisme pour régularisation traversé de rue avec un câble optique, rue de Fiennes 34 - 3. | 2025 |
| 46 m | Change of use | mettre en conformité le changement d'affectation d'un commerce (HoReCa) en un équipement (antenne O.N.E.) | 2024 |
Other nearby cases : 01/PU/1868103, 01/PU/1974115, 01/PU/1983376, 01/PU/1973469, 01/PU/1997324, 01/PFD/2025295, 01/PU/2008575, 01/PU/1936038, 01/PU/1905956, 01/PU/2031299, 01/SFD/1985497, 01/PU/1944899, 01/PU/1839794, 01/GOU_PU/1969562, 01/PFD/1841530, 13/PU/1918089, 01/PU/1839060, 01/PU/2002282, 01/PU/2027613, 01/PU/1937859, 13/PU/1994098, 13/PU/2009655, 13/GOU_PU/2019004, 01/PFD/1991260, 04/PFD/1827956
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)