Granted

Rue de la Conciliation 16

Anderlecht · PU/298351 · Permis d'urbanisme privé

Rue de la Conciliation 16, Anderlecht: new construction. Case octroyé, lodged on 30 March 1906. The decision was notified on 30 March 1906, 0 days after lodging.

construire une maison
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on30 March 1906date the file was received
Decision notified30 March 19060 days
Floor areasnot reported by the source
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
12 mChange of usemettre en conformité la construction d'une annexe et le changement d'affectation du rez de chaussée arrière en lieu de c2025
12 mChange of usemettre en conformité la construction d'une annexe et le changement d'affectation du rez de chaussée côté garage2024
24 mRegularisationrégulariser un immeuble de logements2022
24 mSplit into dwellingsmettre en conformité la répartition des logements2023
53 mRegularisationmettre en conformité un immeuble à appartements2023

Other nearby cases : 01/GOU_PU/1926766, 01/PU/1848400, 01/PU/2015377, 01/PU/2038855, 01/PU/1823872, 01/PU/2018641, 01/PU/1898631, 01/PU/1951248, 01/PU/1826104, 01/PU/1995812, 01/PU/1985251, 01/PU/2015360, 01/PU/1892886, 01/SFD/1925884, 01/PU/1845723, 01/PFD/2013874, 01/PU/1935288, 01/PU/2026888, 01/SFD/1956117, 01/PU/1931889, 01/PU/2026546, 01/PU/2019638, 01/PU/1858780, 01/GOU_PU/1899955, 01/PU/2002245

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)