Rue Brogniez 21
Anderlecht · PU/308548 · Permis d'urbanisme privé
Rue Brogniez 21, Anderlecht: extension or raising. Case octroyé, lodged on 13 June 1936. The decision was notified on 2 July 1936, 19 days after lodging.
couvrir une partie de la cour| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 June 1936 | date the file was received |
| Decision notified | 2 July 1936 | 19 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Façade and windows | transformer la façade au rez-de-chaussée | 2023 |
| 12 m | Façade and windows | transformer la façade avant au rez-de-chaussée + créer une pente dans le hall d'entrée des logements | 2026 |
| 45 m | Façade and windows | remettre en pristin état la travée de gauche au rez en façade avant + isoler les étages de la façade avant par l’extérie | 2024 |
| 45 m | Façade and windows | remettre en pristin état la travée de gauche au rez en façade avant + isoler les étages de la façade avant par l’extérie | 2025 |
| 62 m | Change of use | Transformer un immeuble industriel existant - changement d'affectation, modification des façades, modification au niveau | 2022 |
Other nearby cases : 01/PU/1826539, 01/SFD/1937328, 01/PU/1821006, 01/PU/1895371, 01/SFD/1959797, 01/PFD/1838101, 01/ECO/1842354, 04/PFD/1825950, 01/PU/1909672, 01/PU/2014758, 04/PFD/1824995, 01/PU/1933782, 01/PFD/2044678, 01/PP/2003597, 01/PU/1869045, 01/PFD/1908069, 01/PU/1951391, 01/PU/1850347, 01/PU/2025353, 04/PU/2031632, 04/PU/1870808, 04/PU/1871750, 04/SFD/1903449, 01/PU/2024499, 01/PU/1853183
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)