Rue Bara 112
Anderlecht · PU/325080 · Permis d'urbanisme privé
Rue Bara 112, Anderlecht: demolition and reconstruction. Case octroyé, lodged on 11 July 1968. The decision was notified on 11 July 1968, 0 days after lodging.
démolir et reconstruire le nouveau bâtiment| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 July 1968 | date the file was received |
| Decision notified | 11 July 1968 | 0 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 58 m | Change of use | changer l’affectation d'atelier en commerce du rez-de-chaussée du bâtiment à front de rue et en logement dans l'arrière- | 2025 |
| 74 m | Demolition | Démolir l'auvent de l'entrée sis au 85 rue de France à Saint-Gilles | 2022 |
| 107 m | Public space | Aménager 8 places pour voitures partagées et 2 places pour PMR. | 2022 |
| 112 m | New construction | Demande de construction d'un abri à vélos temporaire sécurisé et d'un atelier Cyclo sur une partie du site Cantilana act | 2021 |
| 119 m | Signs and advertising | adapter la publicité commerciale actuelle au nouveau style maison des hôtels Meininger | 2025 |
Other nearby cases : 13/PFD/1866459, 01/PU/1866830, 01/PU/1866561, 01/PU/1999653, 01/PU/1946030, 01/PU/1929938, 01/PU/2025628, 01/PU/1988929, 01/PU/1934770, 01/PFD/1991410, 01/PU/1847915, 13/PU/1990169, 13/PU/1951202, 01/PU/2023878, 01/PU/1987792, 01/PU/1946194, 01/PU/1867954, 01/PU/2028335, 01/PU/1918734, 01/PU/1933858, 01/SFD/1996583, 01/PU/2036897, 01/PU/1962369, 13/PU/1914002, 01/PU/1863165
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)