Boulevard Poincaré 61

Anderlecht · PU/332855 · Permis d'urbanisme privé

Boulevard Poincaré 61, Anderlecht: heavy renovation. Case octroyé, lodged on 22 October 2002. The decision was notified on 22 October 2002, 0 days after lodging.

transformer
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on22 October 2002date the file was received
Decision notified22 October 20020 days
Floor areasnot reported by the source
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
40 mChange of userénover et transformer un dépôt en un atelier d'artistes2021
40 mExtension or raisingEtendre l'école secondaire 'le collège Matteo Ricci' : aménager 2 préaux et une cage d'escalier extérieure; modifier l'a2022
40 mChange of userénover et transformer un dépôt en un atelier d'artistes2024
47 mSigns and advertisingmaintenir un dispositif publicitaire de 8m22025
57 mPublic spaceCréer deux chambres de pompage enterrées sous le boulevard Poincaré face au square de l'Aviation, en bordure de la zone 2021

Other nearby cases : 01/PFD/1838101, 01/PU/1844730, 01/PU/1853183, 01/PU/1902090, 01/PFU/1959255, 01/PU/2031629, 01/PU/1893666, 01/PU/1830386, 01/PU/2023383, 04/PFD/1957572, 01/PU/2024499, 01/PU/1960028, 01/SFD/1984718, 01/PU/1933871, 04/PU/1870808, 04/SFD/1903449, 01/PFD/1908069, 01/PU/1854309, 04/PU/1914059, 04/PU/2042591, 04/PU/1871222, 01/PFD/2044678, 04/PFD/1928295, 04/PU/1871750, 04/PU/2031632