Granted
Rue Delwart 49–65
Anderlecht · PU/333277 · Permis d'urbanisme privé
Rue Delwart 49–65, Anderlecht: new construction. Case octroyé, lodged on 25 June 2002. The decision was notified on 7 January 2003, 196 days after lodging.
Construction de 5 immeubles à appartements et 48 maisons unifamiliales.| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 June 2002 | date the file was received |
| Public inquiry | 4 September 2002 – 20 September 2002 | |
| Consultation committee | 25 September 2002 | |
| Decision notified | 7 January 2003 | 196 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 77 m | Extension or raising | mettre en conformité le bâtiment : étendre le rez-de-chaussée, réaménager le rez-de-chaussée et le 1er étage, remplacer | 2025 |
| 98 m | Extension or raising | étendre le rez-de-chaussée à l'arrière pour agrandir la cuisine et effectuer des transformations intérieures | 2023 |
| 102 m | Tree felling | abattre 2 arbres à haute tige | 2024 |
| 106 m | Public space | Réaménager la rue Delwart entre les numéros 31 et 101 | 2022 |
| 143 m | Heavy renovation | transformer une maison unifamiliale | 2023 |
Other nearby cases : 01/PU/2034419, 01/PU/1826147, 01/PU/1824509, 01/PU/1866611, 01/PU/1845298, 01/PU/1926873, 01/PU/1897980, 01/PU/1931942, 01/PU/1984553, 01/SFD/1993089, 01/PU/1994386, 01/PU/1966058, 01/PU/1958365, 01/PU/1838194, 01/SFD/1822428