Granted
Rue des Matériaux
Anderlecht · PU/333303 · Permis d'urbanisme privé
Rue des Matériaux, Anderlecht: new construction. Case octroyé, lodged on 15 July 2002. The decision was notified on 1 April 2003, 260 days after lodging.
construction de 46 maisons unifamiliales et de 2 immeubles à appartements| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 July 2002 | date the file was received |
| Public inquiry | 24 October 2002 – 8 November 2002 | |
| Consultation committee | 13 November 2002 | |
| Decision notified | 1 April 2003 | 260 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)