Refused
Rue Mercator 4
Anderlecht · PU/333762 · Permis d'urbanisme privé
Rue Mercator 4, Anderlecht: new construction. Case refusé, lodged on 31 March 2004. The decision was notified on 27 June 2006, 818 days after lodging.
construire un immeuble à appartements| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 31 March 2004 | date the file was received |
| Public inquiry | 24 May 2004 – 8 June 2004 | |
| Consultation committee | 16 June 2004 | |
| Decision notified | 27 June 2006 | 818 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)