Skip to content
AltUrb
Granted

Boulevard International 11

Anderlecht · PU/336069 · Permis d'urbanisme privé

Boulevard International 11, Anderlecht: energy works. Case octroyé, lodged on 22 March 2010. The decision was notified on 20 April 2010, 29 days after lodging.

installer 52 panneaux photovoltaïques
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on22 March 2010date the file was received
Decision notified20 April 201029 days
Floor areasnot reported by the source
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mEnergy worksplacer des installations techniques pour la recharge de voitures électriques2023
0 mEnergy worksposer des installations techniques pour la recharge de voitures électriques2022
127 mNew constructionconstruire un hall industriel et des locaux d'activités productives2024
136 mHeavy renovationtransformer sans changement de volume le permis d'urbanisme 48388 (extension des WC Dames et mezzanine au rez-de-chaussé2023
167 mExtension or raisingconstruire une extension d'un entrepôt2022

Other nearby cases : 01/PU/1938453, 01/PFD/1952064

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)