Skip to content
AltUrb
Granted

Boulevard Industriel 135

Anderlecht · PU/337473 · Permis d'urbanisme privé

Boulevard Industriel 135, Anderlecht: new construction. Case octroyé, lodged on 30 November 2010. The decision was notified on 6 May 2011, 157 days after lodging.

installer une cabine haute tension
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on30 November 2010date the file was received
Public inquiry2 January 2011 – 17 January 2011
Consultation committee20 January 2011
Decision notified6 May 2011157 days
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingconstruire une extension d'un entrepôt2022
48 mNew constructionconstruire un hall industriel et des locaux d'activités productives2024
91 mHeavy renovationtransformer sans changement de volume le permis d'urbanisme 48388 (extension des WC Dames et mezzanine au rez-de-chaussé2023
167 mEnergy worksposer des installations techniques pour la recharge de voitures électriques2022
167 mEnergy worksplacer des installations techniques pour la recharge de voitures électriques2023

Other nearby cases : 01/PFD/1908669, 01/PU/1938453, 01/PFD/1952064, 01/PFD/1966649

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)