Clos de Wagram, Uccle: new construction. Case octroyé, lodged on 15 February 2006. The decision was notified on 18 October 2006, 245 days after lodging.
la construction d'une villa| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 February 2006 | date the file was received |
| Public inquiry | 24 April 2006 – 9 May 2006 | |
| Consultation committee | 31 May 2006 | |
| Decision notified | 18 October 2006 | 245 days |
| Floor areas | — | not reported by the source |
| Competent authority | Uccle |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.