Skip to content
AltUrb
Granted

Rue Gabrielle 95

Uccle · PU/380762 · Permis d'urbanisme privé

Rue Gabrielle 95, Uccle: extension or raising. Case octroyé, lodged on 19 March 2009. The decision was notified on 7 June 2010, 445 days after lodging.

Extension d'un immeuble à appartements
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on19 March 2009date the file was received
Public inquiry31 August 2009 – 15 September 2009
Consultation committee30 September 2009
Decision notified7 June 2010445 days
Floor areasnot reported by the source
Competent authorityUccle

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
47 mRegularisationCela concerne une demande de permis d’urbanisme pour régularisation des infractions A, B et D.2025
48 mHeavy renovationmettre en conformité et transformer une habitation unifamiliale de type 2 façades2022
51 mTree fellingabattre un résineux2021
66 mTree fellingAbattre deux marronniers en urgence2022
72 mExtension or raisingmettre en conformité une terrasse accessible située en façade arrière2023

Other nearby cases : 16/PU/1856680, 16/PU/1899485, 16/PU/2005367, 16/PU/1870314, 16/PU/1943510, 16/PU/1824926, 16/PU/2001158, 16/PU/1970878, 16/AA/1863365, 16/PU/1959830, 16/PU/1994759, 16/PU/2020289, 16/PU/1926414, 16/PU/1898851, 16/PU/1989263, 16/PU/1952497, 16/PU/2043494, 16/PU/1856621, 16/PU/2015099, 16/PU/1985264, 16/PU/2010438, 16/AA/1857390, 16/PU/2008190, 16/PU/1996186, 16/PU/1865156

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)