Granted

Dieweg 69

Uccle · PU/381798 · Permis d'urbanisme privé

Dieweg 69, Uccle: new construction. Case octroyé, lodged on 25 June 2010. The decision was notified on 13 April 2011, 292 days after lodging.

la création d'équipements sportifs et d'infrastructures hospitalières et d'accueil pour adolescents
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on25 June 2010date the file was received
Public inquiry4 October 2010 – 19 October 2010
Consultation committee3 November 2010
Decision notified13 April 2011292 days
Floor areasnot reported by the source
Competent authorityUccle

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mTree fellingAbattage de trois érables2024
0 mOtherplacer une bulle gonflable saisonnière sur 2 terrains de tennis extérieurs2026
0 mTree fellingAbattre un érable en urgence2025
0 mOthermodifier le revêtement du sol des 3 terrains de tennis extérieurs en terre battue synthétique2024
99 mTree fellingAbattage d'un arbre - Régularisation PV/02/20222025

Other nearby cases : 16/GOU_PU/2024578, 16/AA/1914854, 16/AA/1999142, 16/PU/1945574, 16/PU/1907318, 16/PU/2018743, 16/PU/1950398, 16/GOU_PU/1967258, 16/PU/2016885, 16/AA/1866698, 16/SFD/1831740, 16/PU/1996451, 16/PU/2028462, 16/LPFD/1910054, 16/PU/1909539, 16/PU/2010045, 16/PU/1852796, 16/PU/2011548, 16/PU/1964321, 16/AA/1917651, 16/PU/1902797, 16/PU/1935624, 16/PU/2042963, 16/GOU_PU/1907713, 16/PU/1840386

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)