Avenue Charles-Quint 582
Berchem-Sainte-Agathe · PU/383767 · Permis d'urbanisme privé
Avenue Charles-Quint 582, Berchem-Sainte-Agathe: extension or raising. Case octroyé, lodged on 16 December 2010. The decision was notified on 21 March 2011, 95 days after lodging.
Transformation d'un immeuble (construction d'un local technique)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 December 2010 | date the file was received |
| Decision notified | 21 March 2011 | 95 days |
| Works started | 29 April 2011 | |
| Competent authority | Berchem-Sainte-Agathe |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 26 m | Tree felling | Herinrichting van een buitenaanleg | 2022 |
| 60 m | Signs and advertising | Placement d'un panneau LED | 2022 |
| 89 m | Demolition and reconstruction | Démolir et transformer partiellement un complexe de bâtiments en vue de la reconstruction qui accueillera des logements, | 2024 |
| 89 m | Change of use | Occupation temporaire d'un bâtiment existant (bureaux et espaces de stockage en équipements culturels) | 2024 |
| 89 m | Change of use | Demande de permis d’urbanisme à durée limitée visant l’occupation temporaire dans un bâtiment existant. Occupation des a | 2024 |
Other nearby cases : 03/PFD/1953491, 03/PU/2041066, 03/PU/1856173, 03/PFD/1977361, 03/PU/1942258, 03/PU/1911838, 03/PU/1971114, 03/PU/2036998, 03/SFD/1903661, 03/PU/1865435, 03/PU/1822896, 03/ENS/1975740, 03/PU/1822902, 03/ENS/1975737, 03/PFD/1833333, 03/PU/1966375, 03/PU/2021472, 03/PFD/1996559, 03/PU/1996281, 03/PU/1825162, 03/PU/1850371, 03/PU/2020304, 03/PU/1899757, 03/PU/1994359, 03/PU/2009142
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)