Granted
Avenue Napoléon 67
Uccle · PU/403838 · Permis d'urbanisme privé
Avenue Napoléon 67, Uccle: demolition and reconstruction. Case octroyé, lodged on 20 May 2011. The decision was notified on 5 September 2011, 108 days after lodging. The project creates 1 911 m² of housing.
la démolition de la maison existante R+1+T et de son car-port et la construction d'une villa R+11 911m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 May 2011 | date the file was received |
| Decision notified | 5 September 2011 | 108 days |
| Competent authority | Uccle |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)