Skip to content
Altaica Urban
Granted

Avenue de la Brème 3

Auderghem · PU/404903 · Permis d'urbanisme privé

Avenue de la Brème 3, Auderghem: roof. Case octroyé, lodged on 1 July 2011. The decision was notified on 11 October 2011, 102 days after lodging. The project creates 8 m² of housing.

construire une lucarne en toiture avant et arrière d'une maison unifamiliale
The application's own description, in its source language (FR). Source: Nova.
8
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 July 2011date the file was received
Decision notified11 October 2011102 days
Works started26 October 2011
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
13 mFaçade and windowsmettre en conformité les menuiseries en façade avant d’une maison unifamiliale mitoyenne2022
40 mExtension or raisingtransformer et étendre une maison unifamiliale, placer un abri de jardin2024
46 mRegularisationmettre une maison unifamiliale en conformité2022
49 mFaçade and windowsisoler par l'extérieur façade avant, modifier la zone de recul et mettre en conformité les menuiseries d'une maison unif2023
50 mExtension or raisingagrandir et modifier le rez de chaussée ainsi qu'isoler la façade arrière et la toiture2026

Other nearby cases : 02/PU/1800662, 02/AA/1911664, 02/PU/1921659, 02/PU/1978855, 17/PU/1987781, 02/PU/1977524, 02/AA/1871478, 02/PU/1908889, 02/PU/1963671, 02/PU/1992305, 02/SFD/1826849, 02/PU/1975473, 17/PU/1925664, 02/PU/1946283, 02/PFD/1835260, 17/AA/1845161, 02/PFD/1869742, 02/PFD/2031121, 17/PU/1976459, 17/PU/1930456, 02/PU/1959662, 17/PU/1836436, 17/PU/1926201, 17/PU/1827157, 17/PU/1800991

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)